Third party opinion and fixed-fee mediation procedures
Contents |
[edit] Introduction
Construction contracts usually provide for disputes to be dealt with by agreed dispute resolution procedures involving mediation, adjudication and arbitration. Often a combination of all three.
On 6 November 2014, The RIBA launched two new dispute resolution schemes intended as alternatives to more formal processes:
- Third party opinion.
- Fixed-fee mediation.
These are fast, low-cost schemes intended for the resolution of low-level disputes that might otherwise cause delays to projects.
[edit] Third party opinion
The third party opinion procedure is intended for the resolution of technical issues or issues such as valuation. It involves the selection of an independent professional to give an opinion on the dispute and to make a recommendation for settlement. It is appropriate where the parties genuinely wish to settle the dispute and is entered into by consent, it is not part of the contract terms.
Submissions are limited to the two sides of A4 form each party with a maximum of 10 sides of supporting documents. A 5 hour time limit is applied. If a settlement is reached, the parties sign a binding agreement. The procedure may be abandoned at any time.
[edit] Fixed-fee mediation
The fixed-fee mediation procedure is intended for low-value disputes (up to £15,000) that the parties have a genuine wish to settle, and which can be resolved quickly. Mediators are selected from a list maintained by the RIBA to assist negotiations between the parties. If a settlement cannot be reached by negotiation, the mediator may suggest a settlement, but this is only binding if the parties wish it to be. If a settlement is reached, the parties sign a binding agreement. Mediation may be abandoned at any time.
The parties each set out the nature of the dispute on a single side of a A4. Mediation is conducted by telephone for no more than an hour. There can be one or two hours of preparation depending on the amount in dispute.
[edit] Related articles on Designing Buildings Wiki
- Adjudication.
- Alternative dispute resolution legislation.
- Arbitration.
- Breach of contract.
- Causes of construction disputes.
- Conciliation.
- Contract claims.
- Dispute resolution boards.
- Expert witness.
- Housing Grants, Construction and Regeneration Act.
- Litigation.
- Mediation.
- Med-adjudication.
- Med-arbitration.
- RIBA.
- Scheme for Construction Contracts.
Featured articles and news
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding..